As of June 2022
Ongoing Works:
Excavation Works: Completed
Civil/ Structural Works: Ongoing concreting of columns and shear wall at 8th to 9th Floor of Cluster E Area 3
Architectural Works: Ongoing data wall installation at 14th to 15th Floor Cluster H
Mechanical Works: Ongoing installation of toilet exhaust duct at 8th to 12th Floor Cluster H
Electrical Work: Ongoing installation of hangers and supports, feeder line at Cluster F, G , H and I
Plumbing/ Sanitary: Ongoing installation of vent pipes at 16th Floor Cluster G
Fire Protection: Ongoing pipe-sleeves installation at 5th to 8th Floor of Cluster E